Project Management Professional (PMP) — Question 517
A research and development team is finishing up a two year initiative. The project manager is focused on the closing activities for the project.
Which activity should be considered as a priority?
Answer options
- A. Release the resources and plan for a project completion celebration.
- B. Ensure that knowledge transfer activities are executed as planned.
- C. Hold a steering committee meeting to inform them of the project completion.
- D. Mark the product backlog completion status and update the communications management plan.
Correct answer: B
Explanation
The correct answer is B because ensuring knowledge transfer is critical for the continuity of project outcomes and for the benefit of future projects. Options A, C, and D, while important, do not prioritize the transfer of knowledge, which is essential for leveraging the lessons learned and maintaining project benefits.