The deliverables of a project have been completed. However, the stakeholders did not approve the deliverables, because they did not cover the needs of the business.
Which actions should the project manager have taken to avoid this situation?

Answer options

Correct answer: A

Explanation

The correct answer is A because defining the project management plan and ensuring it aligns with project objectives and business needs is crucial for stakeholder approval. Options B, C, and D focus on engagement and feedback but do not directly address the core issue of aligning deliverables with business objectives from the outset.