Project Management Professional (PMP) — Question 496

During a sprint, one of the team members found an issue. According to the team member and the product owner, the issue has a higher level of importance than the other features of the sprint, but is not a roadblock to completing it.
What should the project lead ask the project team do?

Answer options

Correct answer: D

Explanation

The correct answer is D because it emphasizes sticking to the sprint plan while ensuring that the issue is acknowledged and prioritized for future work. Option A is incorrect as it suggests delaying the issue unnecessarily, while B is not suitable since the change control board process is not needed for non-roadblock items. Option C is not appropriate as addressing the issue during the sprint could disrupt the flow and focus on the established tasks.