Project Management Professional (PMP) — Question 496
During a sprint, one of the team members found an issue. According to the team member and the product owner, the issue has a higher level of importance than the other features of the sprint, but is not a roadblock to completing it.
What should the project lead ask the project team do?
Answer options
- A. Avoid the temptation to make any changes and address the issue in the next sprint.
- B. Submit the issue to the change control board (CCB) to evaluate and formally approve a plan to address it.
- C. Address this issue only as it has a higher priority than the remaining features of the same sprint.
- D. Follow the sprint plan by delivering the features established for the sprint and prioritize the issue in the backlog.
Correct answer: D
Explanation
The correct answer is D because it emphasizes sticking to the sprint plan while ensuring that the issue is acknowledged and prioritized for future work. Option A is incorrect as it suggests delaying the issue unnecessarily, while B is not suitable since the change control board process is not needed for non-roadblock items. Option C is not appropriate as addressing the issue during the sprint could disrupt the flow and focus on the established tasks.