Project Management Professional (PMP) — Question 494

A project manager is using a subcontractor for mobile application development. When the project team tests the application, they realize it does not comply with the new company user-interface standards. Even though these new standards were not included in the statement of work (SOW), the subcontractor agrees to the additional scope as long as payment for this additional work is paid immediately.
What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because initiating a change request allows the project manager to formally document the change in scope and evaluate the contractual implications regarding payment. Option A may overlook necessary contract reviews, C incorrectly closes the project without addressing the issue, and D prioritizes immediate payment without proper contract evaluation.