During the sprint planning of a project, the team members have a disagreement about the comparative size of the backlog items and if they would fit into the next sprint.
Considering a hybrid approach, what should the project manager do?
Answer options
- A. Ask an external technical leader to provide input and plan the sprint.
- B. Remove the items from the product backlog since the size couldn't be estimated.
- C. Facilitate the discussion so that the team members can reach a consensus.
- D. Make the decision about the backlog items based on what makes more sense.
Correct answer: C
Explanation
The correct answer, C, emphasizes the importance of team collaboration and consensus-building, which is crucial for effective agile practices. Options A and D undermine team autonomy by relying on external input or unilateral decision-making. Option B is not a viable solution, as it dismisses the backlog items without addressing the actual issue of estimation.