Project Management Professional (PMP) — Question 475

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.
What should the project manager do?

Answer options

Correct answer: A

Explanation

Option A is correct because it allows the project manager to utilize a predictive approach for well-defined items while addressing complexity through an agile approach. Option B delays the project unnecessarily, while C may complicate project management without gaining clarity on the scope. Option D focuses on escalating the issue rather than providing a practical solution to move forward with the project.