Project Management Professional (PMP) — Question 461
The scope of a project is to replace the street signs within a 10-km radius. The client does not want to sign the project closure report if the radius is not extended by 1 km, to be aligned with the council's development plan.
What should the project manager do?
Answer options
- A. Delay the approval and ask the project sponsor for additional funding.
- B. Contact the council and ask for their approval to extend the scope of the project.
- C. Initiate a new project and discuss the request because it came in too late.
- D. Obtain formal acceptance for the completed work and submit a change request.
Correct answer: D
Explanation
The correct answer is D because obtaining formal acceptance for the completed work is essential before making any changes to the project scope. By submitting a change request, the project manager can address the client's desire for an extended radius while ensuring that the original project is recognized as complete. Options A and B do not follow proper project closure protocols, and C prematurely dismisses the current project without seeking a formal resolution.