Project Management Professional (PMP) — Question 456

While monitoring a project at a work site, the project manager notices that the site team's work breaks have increased by a few minutes every week.
How should the project manager approach this?

Answer options

Correct answer: C

Explanation

The correct answer is C because addressing the issue directly with the team fosters communication and collaboration to find a solution. Options A and B are punitive measures that could demoralize the team without addressing the root cause. Option D is also inappropriate as it unfairly penalizes workers rather than addressing the issue constructively.