Project Management Professional (PMP) — Question 456
While monitoring a project at a work site, the project manager notices that the site team's work breaks have increased by a few minutes every week.
How should the project manager approach this?
Answer options
- A. Dismiss some of the workers for failing to adhere to the break policy
- B. Issue a formal written warning to all hourly workers for their break tardiness
- C. Have a meeting with the team to discuss the issue and propose solutions
- D. Reduce payment to the workers due to their extended breaks
Correct answer: C
Explanation
The correct answer is C because addressing the issue directly with the team fosters communication and collaboration to find a solution. Options A and B are punitive measures that could demoralize the team without addressing the root cause. Option D is also inappropriate as it unfairly penalizes workers rather than addressing the issue constructively.