Project Management Professional (PMP) — Question 454

A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its competitors. A new project manager has been hired to change this scenario.
What approach should the project manager propose?

Answer options

Correct answer: D

Explanation

The correct answer is D because a hybrid approach allows the company to benefit from the flexibility and responsiveness of agile methodologies while still complying with industry regulations. Options A and B suggest a full transition to agile without considering regulatory constraints, which could be risky. Option C maintains the current predictive approach, which has already proven to be less effective compared to competitors.