Project Management Professional (PMP) — Question 452
A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members available who are qualified to complete the work.
What should the project manager do?
Answer options
- A. Assess the team member's development requirements and arrange for the team member to receive training.
- B. Seek approval from the project sponsor to use some of the project budget reserve to hire a new resource.
- C. Work with the functional manager to determine an incentive for the team member to complete the project.
- D. Request a substitute for the team member with a new resource who is more skilled in system development work.
Correct answer: A
Explanation
The correct answer, A, focuses on developing the existing team member's skills through training, which can lead to improved performance in the long run. Option B, while it may seem practical, involves additional costs and does not address the immediate development needs. Option C may motivate the team member but does not guarantee skill improvement. Option D bypasses the opportunity for growth and may not be feasible if replacements are unavailable.