Project Management Professional (PMP) — Question 353
During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal impact on project resources. However, the client has only been focused on the next milestone.
How should the project manager approach this situation?
Answer options
- A. Apply additional resources to realize the early deliverable and ensure the next milestone is achieved.
- B. Focus on the deliverable of the next project milestone as per the client's strict instructions.
- C. Review the change management plan to discuss early benefits realization with the client.
- D. Evaluate whether the client's request will add extra features to the project deliverable.
Correct answer: C
Explanation
The correct answer is C because the project manager should engage with the client to discuss the potential benefits of early delivery, which could lead to a more favorable outcome for both parties. Option A may divert resources from the client's immediate needs, while B ignores the opportunity for cost savings, and D does not address the client's current focus on milestones.