Project Management Professional (PMP) — Question 334

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member's deliverables do not meet the requirements.
What should the project manager do first?

Answer options

Correct answer: B

Explanation

The correct answer is B, as it focuses on understanding the root cause of the issue by discussing how the noncompliant deliverables were created, which can help identify misunderstandings. Option A threatens the team without addressing the issue, C focuses on informing the sponsor about delays instead of solving the problem, and D pushes for immediate rework without understanding why the noncompliance occurred.