A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.
What should the project manager do?
Answer options
- A. Support the team in identifying the area of development and address the gap.
- B. Dissolve the team and include the team members in other existing teams.
- C. Identify the struggling team members and move them out of the team.
- D. Set up a clear expectation that the team is to deliver as in their previous projects.
Correct answer: A
Explanation
The correct answer is A because supporting the team in identifying development areas helps them improve and meet project goals. Options B and C do not address the root cause of the issue, while option D may not be realistic in a new domain where previous expectations may not apply.