Project Management Professional (PMP) — Question 301

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?

Answer options

Correct answer: C

Explanation

The correct option is C because estimating the impact of the new feature and consulting with the product owner helps determine if the request is feasible and how it aligns with project goals. Option A is incorrect as escalating an issue without assessing its impact does not address the immediate need. Option B, while collaborative, does not directly focus on understanding the impact. Option D is not advisable as simply increasing capacity may not be practical or effective.