Project Management Professional (PMP) — Question 290

During the course of the project, several obstacles are identified that are preventing the project from moving forward.
What should the project manager do to remove the obstacles?

Answer options

Correct answer: B

Explanation

The correct answer is B because implementing plans to remove obstacles directly addresses the issues hindering the project's progress. Options A and C do not resolve the obstacles; instead, they either divert attention or escalate without action. Option D may help in organizing the resolution process but does not actively remove the obstacles.