Project Management Professional (PMP) — Question 278

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months.
Based on the new timeline, what should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because focusing on high-priority items and developing a minimum viable product (MVP) allows the project manager to meet the tight deadline while still delivering value. Option A may not be sustainable and could lead to burnout, while option C could be unrealistic in terms of budget approval. Option D does not address the need for immediate action to meet the new timeline.