Project Management Professional (PMP) — Question 262
During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B.
What should the project manager do?
Answer options
- A. Ask team B to focus on their backlog and deliver based on their priority
- B. Inform team B of the dependency and ensure that the deliverable is planned
- C. Make team A a part of team B and ensure that the deliverable is ready
- D. Request team B to immediately start this activity and deliver to team A
Correct answer: B
Explanation
The correct answer is B, as it is crucial for the project manager to communicate the dependency to team B and ensure that the deliverable is incorporated into their planning. Option A is incorrect because it overlooks the need for coordination. Option C is not feasible as merging teams may not be practical. Option D is inappropriate as it demands immediate action without proper planning.