Project Management Professional (PMP) — Question 254

On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project manager realized that some of the key activities were scheduled over the holiday periods in the overseas offices.
What should the project manager do next?

Answer options

Correct answer: D

Explanation

The correct answer is D because updating the schedule to reflect holidays and redistributing the workload can help mitigate delays without overburdening any single office. Option A only informs the sponsor of delays without addressing the issue, B adds unnecessary costs, and C may lead to burnout and compliance issues with labor laws.