Project Management Professional (PMP) — Question 233
A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.
What should the project manager do?
Answer options
- A. Suggest that the sponsor conduct a cost-benefit analysis to determine feasibility.
- B. Advise the sponsor that it is not the project manager's job to evaluate the project.
- C. Use the management reserve in order to expedite completion of the deliverable within 2 months.
- D. Change the project methodology in order to achieve completion of the deliverable within 2 months.
Correct answer: A
Explanation
The correct answer is A because conducting a cost-benefit analysis helps the sponsor understand the implications and feasibility of adding the new deliverable. Option B is incorrect as it dismisses the project manager's role in providing guidance. Option C is not advisable without prior analysis, and Option D may not be necessary or effective without understanding the project's constraints.