Project Management Professional (PMP) — Question 233

A project sponsor would like to include a new deliverable. The sponsor contacts the project manager in order to seek advice on the most efficient approach to complete the deliverable within the next 2 months.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because conducting a cost-benefit analysis helps the sponsor understand the implications and feasibility of adding the new deliverable. Option B is incorrect as it dismisses the project manager's role in providing guidance. Option C is not advisable without prior analysis, and Option D may not be necessary or effective without understanding the project's constraints.