An agile project is running its fifth iteration out of eight. After the last iteration planning the team was informed that there is a new competitor in the market, and it is necessary to move faster to ensure market share is not missed.
What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C, as it focuses on finding innovative ways to expedite the product launch, which is crucial given the new competition. Options A and B do not directly address the urgency of the situation, while D may not be feasible as simply increasing velocity without a strategy may not ensure a timely launch.