One phase of a project took much longer than initially anticipated. The key stakeholders expressed their concern regarding a potential project delay.
What should the project manager do?
Answer options
- A. Request additional contingency from the sponsor
- B. Add more float to the overall project schedule
- C. Expedite the next phase to reduce slippage
- D. Organize a root cause analysis (RCA) workshop
Correct answer: D
Explanation
The correct answer is D because organizing a root cause analysis (RCA) workshop helps to identify the reasons behind the delays and allows the team to address any underlying issues. The other options do not directly address the root causes of the delays, which is essential for mitigating further risks in the project timeline.