Project Management Professional (PMP) — Question 190

A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than- planned cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.
What should the project manager have done to avoid this situation?

Answer options

Correct answer: D

Explanation

The correct answer is D because consistently capturing and reviewing project work and costs helps identify discrepancies early on, preventing issues like delayed invoices. Options A, B, and C, while relevant, do not address the proactive management of costs throughout the project lifecycle, which is crucial for avoiding such situations.