Project Management Professional (PMP) — Question 163

A project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones specified within the project charter.
What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because any changes to the project scope must be documented and processed through the configuration management plan and submitted to the change control board (CCB) for approval. Options A and B do not address the need for formal approval of scope changes, while D does not provide a solution for managing the changes but merely raises a concern.