Project Management Professional (PMP) — Question 161

A project manager is working as a servant leader for a pilot project to adopt agile practices. After three sprints, the team demos the product to the main stakeholders, but receives negative feedback about the product's features. The team feels that all the features met the acceptance criteria defined by the product owner and does not understand what went wrong.
How should the project manager mitigate the product rejection?

Answer options

Correct answer: B

Explanation

The correct answer is B because engaging stakeholders in future sprint reviews allows for direct feedback and alignment on expectations, which helps prevent misunderstandings. Option A does not ensure stakeholder involvement during the process, while C focuses only on fixing issues rather than understanding them. Option D shifts blame to the product owner rather than promoting collaboration to enhance the product.