Project Management Professional (PMP) — Question 148

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs.
How should the project manager ensure the work continues smoothly?

Answer options

Correct answer: D

Explanation

The correct answer is D because liaising with the school to schedule nonworking hours during school times helps minimize disruption and ensures the safety of students. Option A is not practical as it delays the project unnecessarily, option B fails to address the school's needs, and option C is unrealistic as it places an undue burden on the school community.