Project Management Professional (PMP) — Question 1402
A project manager is assigned to a project in a company that is transitioning to agile. Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project. However, the project sponsor needs a quick win to ensure the continuation of the project.
What approach should the project manager use?
Answer options
- A. An agile approach as this would provide working functionality earlier
- B. A predictive approach as this would please the senior stakeholders
- C. A hybrid project as this will mitigate stakeholders' concerns
- D. A predictive approach as this will show benefits for all stakeholders
Correct answer: C
Explanation
The correct answer is C, a hybrid project, because it allows the project manager to balance the needs of stakeholders who prefer detailed planning with those who want to see results quickly through agile methods. Options A and B do not address the concerns of all stakeholders, while D focuses solely on benefits without accommodating the need for stakeholder buy-in.