Project Management Professional (PMP) — Question 139
A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.
What should the project manager do?
Answer options
- A. Organize an online distribution channel from another country.
- B. Ask the sponsor to authorize the launch and then wait for approval.
- C. Ask the board to use their influence and speed up the approval.
- D. Work with the team to find ways to bypass the regulations.
Correct answer: C
Explanation
The correct answer, C, is appropriate because leveraging the board's influence can help expedite the regulatory approval process, ensuring compliance while minimizing delays in the launch. Options A and B do not address the regulatory requirements, while option D is unethical and could lead to serious legal repercussions.