A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.

What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer, C, is appropriate because leveraging the board's influence can help expedite the regulatory approval process, ensuring compliance while minimizing delays in the launch. Options A and B do not address the regulatory requirements, while option D is unethical and could lead to serious legal repercussions.