Project Management Professional (PMP) — Question 1378

A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because it emphasizes the importance of communication with stakeholders regarding the delay and evaluating its implications on the project. Options A, C, and D do not prioritize stakeholder engagement and assessment, which are crucial in managing project risks effectively.