Project Management Professional (PMP) — Question 1373

The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies.
What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct choice is C because having a common understanding of agile ensures that all team members are on the same page, which is crucial for effective collaboration. Options A and D may introduce confusion by overwhelming the team with too much information or focusing on a single methodology. Option B is incorrect as it neglects the need for alignment among team members despite their individual experiences.