Project Management Professional (PMP) — Question 1371
A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.
What should the project manager do?
Answer options
- A. Update the stakeholder engagement assessment matrix
- B. Update the communications management plan to include informal requests
- C. Ask the team member to develop a dashboard to fulfill the request
- D. Tell the team member to route the request through the project manager
Correct answer: D
Explanation
The correct answer is D because it ensures that all requests are properly managed and communicated through the project manager, maintaining control over project deliverables. Option A is incorrect as it does not address the immediate request. Option B is not suitable since it does not focus on the specific request situation. Option C bypasses the project manager's authority and could lead to miscommunication.