Project Management Professional (PMP) — Question 1264
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client.
What should the project manager do before sending the information to the client?
Answer options
- A. Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.
- B. Sequence the tasks with estimates and add standard risk reserves to use for software development.
- C. Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.
- D. Work with the team to understand their views and add the appropriate dependencies and risks.
Correct answer: D
Explanation
The correct answer is D because involving the team ensures that all viewpoints are considered, which can lead to better identification of dependencies and risks. Options A and B overlook the importance of team collaboration and risk assessment, while option C fails to include team insights, which are crucial in agile methodology.