During an agile project, a project manager lost one of the resources, and at the same time, uncovered new requirements, which were added to the backlog. What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A because the project manager needs to work with the product owner to reassess the backlog priorities due to the impact on velocity from both the loss of a resource and the addition of new requirements. Options B and C focus on iteration scope and velocity independently, which does not address the immediate need to prioritize the backlog. Option D suggests reviewing the project schedule, but it does not consider the need to adjust backlog priorities first.