Project Management Professional (PMP) — Question 123

During an ongoing project, a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy.
What should the project manager share with the key resource?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the benefits management plan outlines how the project contributes to organizational goals and the expected benefits. The other options, while relevant to project management, do not specifically address the alignment of the project with the organization's strategy.