Project Management Professional (PMP) — Question 121

A project manager is leading a hybrid project that is building an app for a travel industry startup. Due to unforeseen events, the features and the overall solution will not be useable by many customers due to new travel restrictions.

What should the project manager do first?

Answer options

Correct answer: C

Explanation

The correct answer is C because assessing environmental changes is crucial to adapt the project to new circumstances. This allows for an informed pivot that can still provide value, whereas pausing the project (B) does not explore potential solutions, and seeking management advice (D) may delay immediate action. Releasing the team (A) is premature without first understanding the project's viability.