Project Management Professional (PMP) — Question 1201

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks. The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team.
How should the project manager handle this situation?

Answer options

Correct answer: D

Explanation

The correct response is to review the risk management plan, as it allows the project manager to assess the potential impact of the delays and develop mitigation strategies. Options A and B focus on schedule compression techniques without addressing the root cause of the delays, while option C deals with conflict management, which may not be the most effective approach in this situation.