Project Management Professional (PMP) — Question 1188
Midway through the execution of an agile protect there is a shift in the strategic objectives at the organization level to promote digital transformation.
What should the project manager do next?
Answer options
- A. Schedule a meeting with the team to assess the impact of the change
- B. Escalate to the product owner and cancel the upcoming iterations
- C. Prepare a user story to handle the change and assign it to the next iteration
- D. Update the risk-prioritized backlog with the strategic change
Correct answer: A
Explanation
The correct answer is A, as it is essential for the project manager to gather the team to discuss the implications of the shift in strategic objectives. Option B is incorrect because canceling iterations without assessing the impact isn't a proactive approach. Option C, while relevant, does not prioritize team assessment first, and option D fails to involve the team in understanding how the change affects the current work.