Project Management Professional (PMP) — Question 1178
A project manager is assigned to a project. The project schedule and costs are tight, and the project manager determined that there is a lack of resources to deliver this project.
What should the project manager do?
Answer options
- A. Identify the resource requirements and communicate them to the stakeholders seeking resources.
- B. Update the risk register noting that, due to the lack of available resources, the project is likely to be delayed.
- C. Define the work breakdown structure (WBS), identify the resource gaps, and reduce project management activities.
- D. Formalize a scope change request with the stakeholders to adjust the project scope with the available resources.
Correct answer: A
Explanation
The correct answer is A because identifying resource requirements and communicating them to stakeholders is essential for obtaining the necessary resources to move the project forward. Option B does not address obtaining resources, while option C focuses on WBS and reducing activities instead of resource acquisition. Option D suggests changing the project scope rather than solving the resource shortage issue.