Project Management Professional (PMP) — Question 1160

An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.
How should the facilitator proceed?

Answer options

Correct answer: B

Explanation

The correct answer is B because a team charter discussion helps establish the team's purpose, goals, and norms, which is crucial when the team is new. The other options, while valuable, are more suited for later stages when the team dynamics and objectives have already been defined.