An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.
How should the facilitator proceed?
Answer options
- A. Set up a lessons learned session from a similar project.
- B. Hold a team charter discussion.
- C. Schedule a release planning session.
- D. Conduct a product roadmap session with the team.
Correct answer: B
Explanation
The correct answer is B because a team charter discussion helps establish the team's purpose, goals, and norms, which is crucial when the team is new. The other options, while valuable, are more suited for later stages when the team dynamics and objectives have already been defined.