Project Management Professional (PMP) — Question 1152

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

Answer options

Correct answer: A

Explanation

The correct answer, A, emphasizes the importance of delivering incremental working products, which allows teams to gather feedback and make adjustments throughout the project. Options B, C, and D focus on tracking and monitoring aspects but do not directly address the proactive delivery of value as effectively as A does.