Project Management Professional (PMP) — Question 1152
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
Answer options
- A. By focusing on the delivery of incremental working products to the customer
- B. By conducting daily standups to more accurately track project deliverables
- C. By reviewing burnup charts to determine the effort required against estimated earned value
- D. By scheduling iterative meetings with the product owner to improve project tracking
Correct answer: A
Explanation
The correct answer, A, emphasizes the importance of delivering incremental working products, which allows teams to gather feedback and make adjustments throughout the project. Options B, C, and D focus on tracking and monitoring aspects but do not directly address the proactive delivery of value as effectively as A does.