Project Management Professional (PMP) — Question 1150

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management, since there is no project management office (PMO). The managers involved are unaware of their responsibilities for the project.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because providing training to stakeholders ensures they understand their roles and responsibilities, which is crucial for project success. Options B and C suggest delaying or sidelining the training by focusing on establishing a PMO, which does not address the immediate need for clarity among stakeholders. Option D is insufficient as it limits training to only the internal team, potentially leaving external stakeholders uninformed.