Project Management Professional (PMP) — Question 1146
A project has recently kicked off. The project manager observes that there are different expectations among the project team members. These growing misunderstandings are affecting team productivity.
Which document should the project manager use as a guide to resolve the issue?
Answer options
- A. Project organization charts
- B. Project charter
- C. Stakeholder register
- D. Team charter
Correct answer: D
Explanation
The Team Charter is designed to outline the expectations, roles, and responsibilities of team members, making it the most relevant document to address misunderstandings. The Project Organization Charts provide structural details, the Project Charter outlines the project's purpose, and the Stakeholder Register lists stakeholders, none of which directly resolve team expectation issues.