Project Management Professional (PMP) — Question 1144
A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk materialized and the project time line had to be extended by 2 months.
Which two actions should the project manager take? (Choose two.)
Answer options
- A. Ask the team member to work overtime to make up the lime lost so that the project schedule is not impacted.
- B. Log it in the risk register and work with the relevant owner to implement the mitigation action plan.
- C. Analyze the impact of the issue and submit a change request to update the project schedule.
- D. Inform the project sponsor that the risk has materialized and request that the project budget be increased.
- E. Extend the project deadline and update the project schedule to reflect the delay.
Correct answer: B, C
Explanation
The correct answers, B and C, are appropriate because they involve formally addressing the risk by logging it and analyzing its impact, which are essential steps in risk management. Options A, D, and E do not address the need for proper documentation and analysis of the issue, which are critical for effective project management.