Project Management Professional (PMP) — Question 1134

A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one member reported an impediment that requires collaboration from an expert who is assigned to another project.

What should the project manager do first in this situation?

Answer options

Correct answer: A

Explanation

The correct answer is A because checking the expert's availability is the first step in addressing the impediment, allowing the project manager to understand if the needed collaboration is feasible. Options B and C focus on alternative responses that may not address the immediate need for collaboration, while option D does not solve the current issue of requiring external expertise.