Project Management Professional (PMP) — Question 1131

The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two actions should the project manager do? (Choose two.)

Answer options

Correct answer: A, C

Explanation

The correct actions are A and C. Reviewing the customer’s priorities ensures that the project manager understands which requirements are most important, while discussing with the project team helps identify which elements can be expedited. The other options either discourage progress, create unnecessary tension, or escalate the issue without addressing the customer's needs.