Project Management Professional (PMP) — Question 1129

The project manager is reviewing the program risks and issues with key stakeholders. One of the stakeholders wants to understand when the risk may potentially become an issue.

What artifact should the project manager share with the stakeholder?

Answer options

Correct answer: D

Explanation

The Risk Register is the appropriate artifact to share because it contains detailed information about identified risks, including their potential impact and triggers. The Project Management Plan, Issue Log, and Risk Management Plan do not provide the specific details on when a risk might escalate into an issue.