Project Management Professional (PMP) — Question 1120

A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because aligning expectations with functional managers ensures that team members' project contributions are recognized and integrated into their performance reviews. Options B and D do not address the alignment issue directly, and option C, while reassuring, does not provide a concrete solution to the misalignment concerns.