Project Management Professional (PMP) — Question 1109

During the executing phase, a project manager is reviewing the issue log and finds there are outstanding high-priority issues that are still open. Most of the open issues require effort from external domain experts who are not on the project team.

What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because it addresses the need for specialized knowledge by proposing to hire external experts, which is essential for resolving high-priority issues. Option A is impractical as it assumes the team can quickly learn complex domain knowledge. Option C is incorrect as simply closing issues does not resolve them. Option D does not address the actual issues and unnecessarily limits the project scope.