A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important milestone in a week.

What should the project manager do next?

Answer options

Correct answer: D

Explanation

The correct answer is D because asking the vendor for a minimally sufficient quantity can help meet the immediate milestone. Option A, while useful for future planning, does not address the urgent need. Option B delays the project further, and C may escalate tensions unnecessarily when a simpler solution might be available.