Project Management Professional (PMP) — Question 108

Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.

What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because documenting the project issue and providing options allows the project manager to address the unforeseen circumstances effectively. This approach keeps stakeholders informed and opens up alternative solutions. In contrast, rescheduling to online sessions or canceling training does not address the broader impact of the situation, and creating a risk plan may not be necessary if the issue can be resolved with options.