Project Management Professional (PMP) — Question 1078

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members on the team who have more experience with similar tasks.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because asking a more experienced team member to support the struggling member fosters collaboration and knowledge sharing, which can enhance the team's overall performance. Option B is less effective as creating a manual may take time and not provide immediate assistance. Option C removes the struggling team member from the task, which may not help them learn or grow. Option D is unnecessary as it does not address the immediate issue and may disrupt team dynamics.